The new pup and I went out to La Paz this past week for 4 days and got a little work done.
She is a digger dog.
With the vertical rebar set at 4 foot intervals, I can finally set the the first corner which will set up placement for the rest of the addition.
First corner in. A couple of notes - there are no end blocks here, it will all be stuccoed anyway. The vertical rebar should be placed in the footer or drilled in, minding where the open cells are in the block. Now the string lines can be replaced with those string blocks I made way back when I was putting in the front gate. No need for story poles, the corners will go in first then course blocks to fill in.
With the north corner in I have laid out the south corner and started the excavation, with the help of the digger dog. It's too small for a piece of equipment and almost too big for an old man with a pick and shovel. I sure remember the horses I have broken ( or should I say, that broke me ) after a day of digging.